Drive along NW 2nd Avenue near Jeffrey Street and you've seen the same thing for years: chain-link fencing, cart paths that go nowhere, a stretch of green that used to be the Ocean Breeze Golf Course sitting quiet while nothing visible happened. That changes on September 3, when the Greater Boca Raton Beach and Park District breaks ground on the next phase of North Park, the 70-acre eastern half of the old course, at a ceremony held right at the corner of NW 2nd Avenue and Jeffrey Street.
The easy read is "the city finally got around to it." That's not really what happened. The district bought the golf course back in 2018 and financed the purchase with a bond that wasn't due to be retired for years. It paid that bond off in the summer of 2025, nearly seven years ahead of schedule, and that payoff is what freed the east side for construction. A second, separate debt, this one owed directly to the city for the property's west side, is still being paid down, which is why the western half of North Park remains stalled while the eastern half moves forward.
That distinction explains everything else converging on this site right now. It's why a Traffic Garden opened here last September, why a racket sports facility is close to finished, why a 42,000-square-foot skatepark just cleared a City Council workshop, and why a proposed surf lagoon is still sitting in committee. These projects were never on one shared timeline. Each has its own funding agreement, and this fall happens to be the moment several of those agreements matured together.
The Debt That Was Actually the Holdup
Ask a longtime Boca Teeca resident why North Park took so long and you'll get some version of the same answer: money, not planning. District executive director Briann Harms told commissioners in mid-2025 that the west-side debt owed to the city was expected to clear around January 2026. The east side had already been released months earlier by the bond payoff, which is exactly why Butters Construction & Development is the contractor breaking ground on September 3 for roughly 70 of the property's approximately 212 acres, not the whole site the district acquired back in 2018.
District Chair Bob Rollins described the groundbreaking as delivering "another example of the kind of high-level recreational facility they have come to expect from the District." The Florida Department of Environmental Protection will also be on the ground overseeing soil mitigation, since decades of golf course chemical use left contamination the district now has to clear as it builds. The project is being designed to meet Sustainable SITES Initiative standards, a certification framework used for public sites built with long-term environmental impact in mind.
Four Projects, One Compressed Window
Here's what's actually converging in roughly the same 12 months, after years where the site barely changed:
- The Traffic Garden, a car-free bicycle and road-safety course built on former tennis courts along Jeffrey Street, held its ribbon-cutting on September 4, 2025.
- Boca Paddle, a 19-pickleball and 6-padel court complex built through a public-private partnership with the district, broke ground in June 2025 with a grand opening expected sometime this year.
- The September 3 groundbreaking covers trail systems, greenways, playgrounds, and event infrastructure across the 70-acre east side.
- A 42,000-square-foot skatepark cleared design approval in January and went before City Council for a permitting workshop in July.
The Traffic Garden matters here as more than a nice amenity for kids on bikes. It's the proof of concept that the rest of this build is following: convert a piece of the old course, get it open fast, then use that momentum to justify the next phase. The September 3 groundbreaking lands just one day short of the Traffic Garden's first anniversary, which is a tighter turnaround than anything else on this property has managed in the seven years since the district bought it.
The Skatepark Boca Teeca Didn't Ask For First
The skatepark heading to North Park exists because of a project that has nothing to do with Boca Teeca. The city's downtown government campus redevelopment is displacing the Tim Huxhold Skate Park, and North Park is where its replacement is landing, at 42,000 square feet, tucked next to Boca Paddle south of Jeffrey Street. The design keeps every skating feature more than 300 feet from residences, with landscaping built in specifically to buffer noise.
The design itself came out of a public workshop that brought in local skateboarders and BMX riders, including Boca Teeca resident and professional skateboarder Fabiana Delfino, who has been outspoken about what access to a facility like Huxhold meant for her career. When the district's commissioners unanimously approved the final design in January, Commissioner Erin Wright called it something that's "going to serve so many people." Not every neighbor agrees it belongs here. Some Boca Teeca residents have pushed back on the siting, and at least one city council member has floated keeping a replacement skatepark closer to its old downtown footprint instead. The district has contracted with American Ramp Company to build it and says the crew is ready to mobilize as soon as city permitting clears, with the city covering roughly two-thirds of construction cost and the district covering the rest.
The One Piece Nobody Has Decided Yet
Not everything on this list is locked in. A proposed Boca Surf Park, an artificial wave pool using Wavegarden Cove technology, is one of several development proposals the district is still evaluating for financial feasibility on the west side. It would sit on roughly 24 acres in the northwest section of the property, with parking and a buffer separating it from nearby condos. It's also the single feature drawing the most concern from Boca Teeca residents, who are watching buffer distance and noise closely given how close the proposed footprint sits to existing homes. Nothing here is final, which is worth knowing if you're the type who checks district meeting agendas before believing a rendering.
What This Actually Looks Like on Your Street This Fall
If you live near NW 2nd Avenue and Jeffrey Street, expect fencing, staged equipment, and soil work to become part of the daily view starting in September. Trail and playground construction on the east side will take months to finish, running alongside the final stretch toward Boca Paddle's opening and the still-pending skatepark permitting. The Boys & Girls Club of Boca Raton has also been approved for a larger facility on the property, adding one more name to a project list that spent years as a master plan on paper and is now mostly under contract.
None of this required anyone to buy or sell anything to matter. It's simply what's changing three blocks from where a lot of East Boca residents already live, and the reason it's all landing now instead of two years ago or two years from now comes down to a bond payoff most people never heard about.